The turn-key project covers the construction of 41.6 km road section between km 472.8 and 514.4 with the following work items:
-Site survey and mapping topographical survey
-Quarries and borrow areas
-Earth works operations (733,111 m3)
-Production of Aggregate with different fractions (451,600 ton) -Screening and crushing operations
-Base Course Pavement (79,112 m3)
-Cement of Sub-base (120,000 m3)
-Bituminous hot pavement operations. (110,250 m3)
-Pipe and Box culvert (13 Pcs)
-Road Furniture and other miscellaneous works
Kazakhstan
COMPLETION DATE: 2014
CLIENT: Ministry of Transport and Communications Republic of Kazakhstan